PT Waskita Karya (Persero) Tbk aims to complete the construction of Phase 1B Velodrome-Manggarai of LRT Jakarta project which spans the total length of 6.4 km to be completed in 2026 and to start its operational in 2027. Currently the construction progress of Phase 1B has reached the concrete casting of slabdeck viaduct with the total length of 1.4 km and the installation of the third rail of the Velodrome Station line heading to Rawamangun Station. The Rawamangun Station construction progress itself has reached 38.04%.