PT Adhi Karya (Persero) Tbk states that the progress of the First Phase of Greater Jakarta LRT Project, as of 22 May 2020, has reached 71.2%. The detail of the progress including service line 1 of Cawang-Cibubur at 85.7%, service line 2 of Cawang-Kuningan-Dukuh Atas at 65.9% and service line 3 of Cawang-East Bekasi at 64.8%.