The Toll Road Agency (BPJT) of the Ministry of Public Works and Housing (PUPR) has stated that the construction progress of the Semarang-Demak Section 2 of Sayung-Demak toll road has reached 80.63% and is aimed to be completed by the end of 2022. The toll road with the total length of 27 km comprises two sections namely Semarang/Kaliwage-Sayung of 10.69 kilometers in length and section 2 Sayung-Demak of 16.31 kilometers in length.