The Minister of Public Works and Housing (PUPR) Basuki Hadimuljono stated that the construction progress of IKN Toll road Section 6B and IKN Toll Access 6C is aimed to be completed in June 2025. Currently, the physical progress of Section 6B has reached 41% with Brantas Abipraya-Bumi Karsa CPA as the contractor, meanwhile the construction progress of Section 6C has reached 77.35% with PP-Waskita-YPP KSO as the contractor.