Kertajati Airport Expects Cisumdawu Toll Road Completion in 2020
Thursday, 5 September 2019
The Toll Road Regulatory Agency (BPJT) of the Ministry of Public Works and Public Housing (PUPR) states that that the 60.84 kilometer Cisumdawu Toll Road to be operational in 2020. The construction of Section I and II of 27.62 kilometers which to be constructed by the government has reached 66.01% and the land acquisition of approximately 86.61%. While the construction of Section III until VI of 33.22% kilometers to be constructed to PT Citra Karya Jabar Tol (CKJT) has reached 9.3% with land acquisition reaching 15.15%.
Kompas.com – September 05, 2019