JORR Elevated Cikunir-Ulujami Toll Road Construction Starts in February 2024
Monday, 20 November 2023

The Jakarta Elevated Outer Ring-Road (JORR) Cikunir-Ulujami toll road project may start construction in February-March 2024, earlier than the previous target. Previously, the construction based on Toll Road Management Agreement (PPJT) was planned to last for 33 months starting from July 2024 until March 2027 with the operation planned for April 2027.